We had the monthly meeting with Oscom.
The project is progressing with a delay of between 4 and 6 weeks. You can check the roadmap here: Notion – The all-in-one workspace for your notes, tasks, wikis, and databases..
In the meeting, we discussed the possibilities for the project to catch up, respecting the roadmap so that it aligns with the contract. They currently have sufficient funds to complete #Rounds 2 and 3. That’s why the project’s contract will remain paused and in the next meeting, we will review the status to decide if it can be unpaused or extended. The official update #4 was missed, which is why they did Update #5 covering 2 months of updates.
The next steps are:
- Complete #Rounds 2 and 3, launch #Round 4.
- Complete the Improvement of the project’s GitHub to not depend on GDrive.
- Solve the delay, maintain the pause, or request an extension of the contract.
Feel free to add any information or comments!