Author: 0xedf458ce355c755e1973778b51b917066d4c0bad
Update Status: Late
Project Health: On Track
Introduction
The main goal of first few months is migration to SDK7
Highlights
The team is working on migration only.
Here is a real-time change-log of migration
90% of migration is done and we plan to finish it until the and of the month according our roadmap
Blockers
With the new SDK7, there are some serious roadblocks. Several features are broken. All of these issues were reported to the SDK7 channel, but many of them have not yet been fixed. Examples include The client screen’s resolution
Next steps
The next steps are according roadmap is decentralisation