Determining Maximum Pause Duration for Projects Delayed
Summary
Determine the maximum pause duration of the project delay.
Abstract
The proposal aims to set a new requirement for the Grants Program, to deal with cases where the vesting contracts of the projects are on pause due to goals not being achieved in the time frame proposed.
Motivation
There is no specified maximum duration when a pause is requested by a grantee due to delays.
Specification
The proposal aims to set the maximum pause duration of the vesting contract due to delays over the project and the framework that the people involved (Grantees, Grant Support Squad, DAO Committee, Revocations Commmittee, Community members) should be going through, depending on the cases.
The Grantee can request a pause on the vesting contract due to delays on the project. The pause will have a maximum duration of three months then, the procedure will be as follows:
-
The Grant Support Squad (GSS) will check if the project has caught up and If the project is on track again:
- A new vesting contract can be created, requested by the GSS, with the period and funds remaining according to the original time frame proposed and considering the duration of the pause.
- The original vesting contract will be unpaused if the project is on track according to the original roadmap and goals.
-
If the grantee requests an extension of the pause granted (not exceeding three months), the project will be sent to the Revocations Committee (RC).
- After that, if the project is on track again, a new vesting contract will be created, requested by the RC, with the period and funds remaining according to the original time frame proposed and considering the duration of the pause.
-
if the grantee requests another extension to the Revocations Committee, the project should pass through a poll (created by a member of the Revocations Committee) to the Community, where they decide by a simple majority if the extension should be granted again.
-
If the grantee decides to step down, the vesting contract will be revoked.
Impacts
This proposal seeks to establish a clear and fair framework for managing delays in projects funded by the DAO
Implementation Pathways
Include the requirement and the new flow proposed in the Grants program documentation.
Also, in the public Grant Support Squad - Manual of Operations
Conclusion
This proposal seeks to establish a clear and fair framework for managing delays in projects funded by the DAO